Business office construction update

Sharing forward an update on the progress of the new business office renovation, as significant strides have been made towards its completion.

Key highlights:

  • Painting and wall coverings– are done
  • Ceiling Installation – the ceiling team is on-site to install the ceiling frame work. Following that, the sprinkler team is scheduled to drop the sprinklers into each area.
  • Office “Tour” – look for an invitation in the upcoming weeks.
  • Anticipated Completion Date – August. With the current progress rate, there is optimism that the space will be ready by late July. However, the remaining tasks involve rolling in the carpet, installing the wall panels, wiring the wall panels and finalizing the ceiling.

We appreciate your patience and cooperation throughout this entire construction project.