Dates: 8/14 – proposed finished date 2/12/18
Note: Dates listed are approximate; please remember to allow for flexbility as issues sometimes arise that couldn’t be planned for.
What’s Happening?
- Installation of construction fencing around main entrance in preparation of MAIN ENTRANCE closure, on 8/14
- Parking and entrance area will be blocked off the evening of 8/13
- Signage is being printed redirecting patients to our Emergency Entrance
- Beginning 8/14, extra volunteers will be available and VIP hours will be extended
Who is impacted?
- All staff
- Patients
Who to contact if you have questions:
- Your supervisor or manager
- Mark Vizenor x3475
- IT x9191
- EVS x3953
- Kim Carlson, x3610 (for volunteers)
- Brenda Moos, x3335 (for Registration)
- Patty Paul x3363 (for Rehabilitation Services)